The State Route 120 at Satellite Boulevard intersection experiences congestion during evening commute hours, and future growth and development in the area is expected to create further delays during both morning and evening peak hours.
The Sugarloaf CID, in partnership with Gwinnett County DOT, has completed an initial traffic study that identified the most viable solution as: dual right-turn lanes on Satellite Boulevard northbound, an extension of one of the dual left-turn lanes on SR 120 westbound, dual left-turn lanes on SR 120 eastbound, and dual left-turn lanes on Satellite Boulevard southbound.
Traffic flow improvements to the State Route 120 at Satellite Boulevard intersection to reduce traffic delays for these two major corridors.
An initial concept for improvements has been developed. We need to identify additional funding for the preliminary engineering, right of way, and construction phases of the project.